nEO slipform

Shaft Tunnel Wall Slip Form + Precast Stair & Slab 조립공법

Shaft Tunnel Wall Slip Form + Precast Stair & Slab 조립공법

The Slip Form method is a type of special hydraulic form of the existing on-site casting method. After pouring the concrete, when the strength of the concrete is greater than that for self-support, it moves upward and continuously repeats rebar assembly, concrete pouring, and curing to complete the structure. It is suitable for safety, shortened construction period, and high-quality structures.

applied area

Features of construction method

UPPERDECK

Distributed loading of rebar and miscellaneous materials

Concrete hopper installation and jack rod connection assembly

MIDDLE DECK

Wall rebar assembly and hydraulic pressure increase

Concrete pouring and other work

HANGING DECK

Concrete surface finishing work

Curing check and bracket installation work

Better than other existing methods
Safe and effective advanced technology

1

stability

check

Slipform 3-layer structure indoor work space work

done

PC SLAB and staircase assembly and installation: simple and convenient

2

economics

check

Reduction in construction costs compared to construction period

done

Wall construction height: 2.0m/day (daytime), 4.0m/day (daytime/night)

done

PC SLAB and stairs: 1st to 2nd floor/1 day installation

3

Constructability

check

Concrete wall structure integration

done

Convenient slip form construction and PC assembly method

done

Advance preparation required depending on ready-mixed concrete supply time

4

quality

check

Factory production: high quality PC SLAB and
PC stairs application

done

Excellent finish for lower concrete wall treatment after slip form rises


02

Horizontal structures (slabs,stairs)

Features of construction method

PC SLAB and staircase installation method

2. Install PC SLAB on the (steel, string) bracket

3. Installation of PC landing and PC stairs on (steel, string) bracket

Bracket installation (slip form lower workbench)

PC stair installation

PC SLAB Installation


NEO technology service

Construction sequence

1. Transport inside the slipform divided vertical sphere

2. Completed installation of slip form inside vertical shaft

3. Construction of horizontal joint connection during slip form rise

4. Internal wall: rebar assembly

5. Circular wall rebar assembly / concrete pouring

6. Surface finishing (lower workbench + bracket installation)

7. Vertical sphere slip form elevation completed (staircase elevation)

8. Slipform disassembly / removal

9. Vertical wall construction completed

10. Installation of stairs (installation of landing on bracket and then installation of inclined stairs)

11. Filling caulking finish after PC SLAB installation